The order to book stage inspections on a Mickleham build

Where the windows are in a Hume corridor program.

Owner Inspections · Mickleham 3064 · 2026-03-04

In short: Trades follow each other closely here. These are the points where work disappears and the window to see it.

The program sets the window

A volume build in Mickleham runs to a fixed program. The gap between one stage finishing and the next covering it is usually two or three days.

Slab pre-pour

The day before the pour. Waffle pods, laps, cover and capping are visible now and never again.

Frame

Where every serious structural finding on our Mickleham jobs has come from. Bracing, slab level and truss bearing.

Lock-up

Sarking, cladding clearance and window flashings, in the days before the plasterer arrives.

Waterproofing

After the membrane, before the tiler. We have found waterproofing incomplete at this point here.

Pre-handover

A week before practical completion, so the list is with the builder before you sign.

Written by the Owner Inspections team from inspections carried out in Mickleham. Licensed building practitioners, Building & Plumbing Commission registration CDB-U 53425.

Guides

More new construction stage inspections guides for Mickleham

All guides →

Book a building inspection in Mickleham

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Questions Mickleham owners ask about this

Which two matter most?

Frame and pre-handover.

How much notice?

A day or two, but flag the date early.

Do dates move?

Constantly, so keep us updated.

Can I book all seven?

Yes, and it gives the fullest record.